SmartSection is developed by The SmartFactory (http://www.smartfactory.ca), a division of INBOX Solutions (http://inboxinternational.com)
Sections > Superintendent Report > Operational Services > Operational Services - Maintenance Report: September 24, 2007
Operational Services - Maintenance Report: September 24, 2007
Published by Cecilia MacDonald [CeciliaMacDonald] on 09/27/2007 (2629 reads)
Operational Services - Maintenance Report: September 24, 2007

Superintendent's Report - Operational Services - Maintenance - September 24, 2007



Maintenance Report
Work Completed or In Progress
July 13-September 17, 2007
BuildingWorkCompleted/
In Progress
Ashby ElementaryAsphalt Completed
Baddeck AcademyAsphaltCompleted
Bras D'Or ElementaryInstalled 3 sign postsCompleted
Breton Education CentreInstall section of new roof (upper section) material ordered In Progress
AsphaltCompleted
Ran 170' fencing 6' high at back of cafeteria parking lot & 84' guardrail on the side of same lotCompleted
Duct cleaningCompleted
BridgeportAshpaltCompleted
New security alarmCompleted
Brookland23' 8' high fence around rock pile hazardCompleted
CabotNew bus garage (starting interior)85% completed
New tanks for interior to replace cistern tank in groundCompleted
New hanidcap ramps with railingsCompleted
AsphaltCompleted
New security systemCompleted
Cabot Bus GarageStack for furnace, washroom ventilationCompleted
CornwallisAsphaltCompleted
CoxheathAsphaltCompleted
New P.A. systemCompleted
DonkinNew gym under construction94% completed
New security alarmCompleted
Dr. TL SullivanNew handicap washroom (waiting for new handicap lift)Completed
Install LED projectorsIn progress
Asphalt Completed
Renovations to one classroomCompleted
FJ AngotStart installing new roof95% completed
FlorenceAsphaltCompleted
New P.A. systemCompleted
GeneralPreventative maintenance on ventilation systemsOngoing
Regular boiler cleaningOngoing
Replacing broken windowsOngoing
Checking water qualityOngoing
Install door bells for security - various schoolsIn progress
Change out EMS controls in panelsIn progress
Sprinkler tank inspections (various schools)Completed
Painting of schools by students, casual and 10-month CUPE workers (various schools) (see separate reports attached)Completed
Refinishing gym floors (hardwood and tile) (various schools)Completed
Checking fencing and paving (various schools)In progress
Wiring project for security (various schools)In progress
George D LewisGym renovationsCompleted
Glace Bay ElementaryConstructing new Snoozlen Room (waiting for new handicap lift)Completed
Glace Bay HighPricing lighting for student parking lot--installing pole lightsIn progress
Sidewalk being constructedCompleted
AsphaltCompleted
Installed 3 sign postsCompleted
IonaTo extend soccer field fence 10' high 532'In progress
Asphalt of basketball court and extensionIn progress
Installing parking lot lightingIn progress
John Bernard CroakRemove lockersIn progress
MacDonald ElementaryReplaced 185' fencingCompleted
Malcolm Munroe To fence in players' benchesPending approval
Marion BridgeRemove and repair rotten floor joists and lower section of walls in new sectionIn progress
New wall for privacy in front of washroom doorCompleted
Paint main foyerCompleted
AsphaltCompleted
Memorial HighUpgrade training area with new machinesIn progress
Installed 5 sign posts and removed old postsCompleted
Duct cleaningCompleted
McLennan Jr HighAsphaltCompleted
New security alarmCompleted
Need ramps installedPending approval
Memorial HighAsphaltCompleted
Working at electrical for vocational equipment purchasedIn progress
Mira RoadTwo offices in Main OfficeCompleted
Two new offices in Library50% completed
Two new staff washroomsCompleted
Upgrade windows in Library85% completed
Parking lot expansionCompleted
AsphaltCompleted
Rewire P.A. systemCompleted
New office area and washrooms areas in Library areaCompleted
MorrisonNew heating systemCompleted
Mount CarmelInstalling video surveillanceCompleted
P.A. system upgradeCompleted
MountainviewNew security alarmCompleted
RankinRan 235' fencing 4' high from soccer field up along walkwayCompleted
Fuel system for busses being installedIn progress
Fence height around soccer field being raisedIn progress
Parking lot lighting being installedIn progress
Riverside ElementaryAsphaltCompleted
Riverview HighNew lobby addition -- Phase II design70% completed
Duct cleaningCompleted
Robin Foote ElementaryAsphaltCompleted
St. Anne's ElementaryExtended dumpster compoundCompleted
St. Joseph (SM)New siding on old sectionIn progress
Renovations to Resource RomCompleted
Office renovationsCompleted
New walkways at front of building waiting for repairs to lawn93% completed
AsphaltCompleted
Upgrade ventilationCompleted
St. Joseph's (NS)Need ramps installedPending approval
St. Mary'sNew security systemCompleted
St. Michael's Jr. HighFencing repairs around back of buildingIn progress
Moving computer lab and construction LD RoomCompleted
Moving Learning CentreCompleted
Sherwood Park Elem.AsphaltCompleted
Southside Learning CtrAsphaltCompleted
Sydney AcademyMusic/change room additionIn progress
New P.A. systemIn progress
P.A. system upgradeIn progress
Renovations to Learning Centre to accept student from WPM95% completed
Fence in transformer to be pricedPending approval
Sydney Mines Jr. HighRenovations to first floorCompleted
New main entrance door systems96% completed
New Science Lab94% completed
New roof95% completed
All downstairs ventilationCompleted
Renovation to Home Ec lab stationIn progress
Sydney River Elem.AsphaltCompleted
ThompsonNew roof95% completed
Security system upgradeIn progress
Need ramps installed off parking areaPending approval
Whitney Pier MemorialNew security systemCompleted