Sections > Superintendent Report > Operational Services > Operational Services Report: September, 2008
Operational Services Report: September, 2008
Published by Cecilia MacDonald [CeciliaMacDonald] on 10/03/2008 (3494 reads)
Operational Services Report: September, 2008

Operational Services Report

September 2008

Capital Construction Committee Visitation

The School Capital Construction Committee made a visit to the Cape Breton Victoria Regional School Board on Monday, September 15, 2008. The mandate of the Committee is to deal with Capital Construction requests of all school boards. We sent our list to the Committee in July 2008. Committee member met with our staff and board and visited 12 sites contained in our submission. After their visits, to all boards, scoring will take place and a report generated with recommendations for the School Construction and Addition /Alterations projects for the Minister′s consideration.

We had seven members visit our sites along with Paul Oldford and Ambrose White. A presentation was made to the Committee at lunch time with several school board members present along with Senior Staff. We received a very good hearing and look forward to a positive response to our request.

Riverview High and Sydney Academy High – Additions/Alterations Update

There was a tremendous amount of work done at Riverview and Sydney Academy over the summer months. The gymnasium at Sydney Academy remains to be completed and, hopefully, it will be done by the end of October.

The Riverview project is near completion to this point. The new Guidance offices etc will be completed and furnished in early September.

Further reports on this project will be forth coming in October.

Summer Painting

There was a great deal of painting done in our schools by students this past summer. Some of this will be referred to in the Maintenance Report that follows.

Maintenance Report – Work Completed/In Progress – Jun 9-Sep 22, 2008

Building

Work

Complete/In Progress

Baddeck

- Upgrade Computer Lab

Complete

BEC

- Install Floor Mop Sinks (all cleaning closets)

- Construct new Trades Lab (waiting for overhead door to be installed)- also, relocating outside Storage

50% Complete

95% Complete

Bras d′Or

- Relocate Playground

- Move Computer Lab

50% Complete

Complete

Cabot

- Pricing new Windows

- Change Fire Alarm System

- Installing new windows in half the building – Contracted to Stott Aluminum to install

- Upgrade lighting with ballasts/tubes

Complete

Complete

In Progress

Complete

Cornwallis

- Install Video Security

- Construct new handicap washroom (waiting for change table)

25% Complete

95% Complete

Cusack

- Install Video Security

50% Complete

Donkin

- Work to be done after Fire Marshall′s Report

Complete

East Bay

-New Exterior Door Ordered (Sydney side)

Complete

General

- Preventive Maintenance on Ventilation Systems

- Regular Boiler Cleaning

- Replacing Broken Windows

- Checking Water Quality

- Install Door Bell for Security (various schools)

- Change EMS Control in Panel

- Wiring Project re Security (8 buildings remaining)

- 2007/08 Fire Alarm Inspections

- Preparing for Summer Work

- Sweeping Parking Lots

- Asbestos Abatement at various building over summer (on going)

- Students, 10 month employees and casual painters painting various schools over summer

- Sprinkler inspections at all schools with System

- Students Mowing Grass and Moving over summer

Ongoing

Ongoing

Ongoing

Ongoing

95% Complete

95% Complete

In Progress

Complete

Complete

Complete

Complete

Complete

Complete

Complete

George D. Lewis

- Pricing new Main Entrance and Install

- Pricing on Window Upgrade (cancelled due to budget

Completed

Glace Bay High

- Pricing for Lighting Student Parking Lot and Installing new Light Poles (meeting with NSP)

- Work to be done after Fire Marshall′s Report

- Upgrade PA System

- Upgrade lighting with ballasts/tubes

In Progress

Complete

Complete

Complete

Greenfield

- Install Walking Track

- Remove Foot Bridge and Install Culvert

- Pricing Parking Lot Renovations

In Progress

Complete

In Progress

John Bernard Croak

- Upgrade Florescent Fixtures throughout School

Complete

MacDonald Elem

- Pricing Soccer Field Fencing

- Upgrade lighting with ballasts/tubes

In Progress

Complete

MacLennan Jr. High

- Security System Upgrade (door contacts)

- Upgrade PA System

85% Complete

Complete

Malcolm Munroe

- Fence Players Benches

- Fire in School - waiting for new computers and washing machine

In Progress

90% Complete

Memorial High

- Working on Electrical for Vocational Equipment

- Construction of Learning Centre(waiting for ventilation unit and countertops)

- Repair Bleachers in Gym (Metal Work)

- Pricing 2nd Phase New Windows (cancelled due to budget)

- Upgrade Domestic Hot Water System (on order)

In Progress

93% Complete

Complete

Complete

Mira Road

- Pricing New Exterior Entrance(cancelled due to budget)

- Upgrade PA System

Complete

Morrison

- Installing Used Furnace

Complete

Mount Carmel

- Installing Mop Sinks

80% Complete

Riverview High

- New P. A. System

- Tender out for 2 sections of Roof and install

- Tender out for redesign of Entry and contract

- Construct 6 new washrooms (waiting to complete deficiencies on last 2 washrooms)

95% Complete

40% Complete

Complete

97% Complete

Robin Foote

- Installing Roof Fans

- Security System Upgrade (door contacts)

- Upgrade PA System

50% Complete

85% Complete

Complete

St. Anne

- Renovations to Library (waiting for curtains)

Complete

St. Joseph (NS)

- Pricing Window – 2nd Phase (front of bldg) (cancelled due to budget)

- All new exterior lighting

Complete

St. Joseph (SM)

- Paving of Lot

Complete

St. Michael′s Jr. High

- Upgrade Fluorescent Fixtures throughout Building

In Progress

Sydney Academy

- Music/Change Room Addition

- Upgrade 4 washrooms

-Upgrade gym and Heating in classroom

- Upgrade PA System

Complete

Complete

60% Complete

Complete

Sydney Mines Jr. High

- Pricing new Window

- Construct 2 new classrooms behind stage

- Installing new Windows

Complete

98% Complete

In Progress

T.L. Sullivan

- Heaters for Gym (on order)

Complete

Thompson

- Security System Upgrade (door contacts)

- Install Ramps off Parking Lot

- New Offices for Cathy Viva(waiting for doors)

- Pricing Windows - two end sections

- New Lunch Room

- Install windows in 2 sections of building

Complete

Pending Approval

Complete

Complete

Complete

In Progress

Whitney Pier Memorial

- Pricing New Windows (cancelled due to budget)

- Install Sections of Flat Roof (2) (behind due to weather)

In Progress

80% Complete

Technology Report – September 2008

S.A.P. Daily Tasks

Since June we went through all the buildings upgrading Deepfreeze on approximately 5000 computers in the classrooms. We also upgraded servers, giving them larger hard drive capacity. In total we did 11 upgrades - as well as complete rebuilds at Glace Bay High School. We also did routine maintenance repairs in all buildings across the CBVRSB. This also includes a major virus at Shipyard Elementary - inventory in a number of schools.

Internet Connectivity

Eastlink internet installs are ongoing. We have seven schools left to change over to the Eastlink fiber optics circuit. This is making a vast difference in school′s internet bandwidth.

Computers for Schools

Since June, the Technology Department with help from Computers for Schools installed over 190 computers in our board. This includes a complete lab in Malcolm Munroe, John Bernard Croak and over 70 in Glace Bay High for a lab. Also, upgrading of obsolete equipment and approximately 13 machines went for donation.

Refresh

During the summer months we did extensive P3 refresh: 34 computers in Jubilee, 32 computers in Riverview, network upgrade in Riverside and installation of assorted peripherals in remaining schools.

Boularderie

We installed and configured over 40 computers - also, cameras, laptops, etc.

I.E.I.

We installed and configured over 100 complete computer systems.

Transportation Report – September 2008

On September 2, 2008 an In-service was held at Malcolm Munroe Jr. High for bus drivers and bus aids. This was a welcome back and start up meeting.

Stephanie Johnston, Manager of ACAP Nova Scotia did a presentation on anti-idling. This presentation was the beginning of our campaign to reduce green gas omissions around school grounds. Along with this presentation was a hands on display of the new vehicles which were added to the fleet for the new school year. The new vehicles are manufactured with exhaust systems that do not tolerate excessive idling.

Drivers were introduced to an updated bus routing software that is now web based. They can view their own bus run, update the run and submit it to the Transportation Department for approval. This has proven to be popular with some of the drivers.

The plan is to elaborate on the Anti-Idling Program for the October In-service. The guest speaker is expected to confirm the presentation time and date in the near future.