Sections > Superintendent Report > Operational Services > Operational Services Report: November, 2008
Operational Services Report: November, 2008
Published by Cecilia MacDonald [CeciliaMacDonald] on 11/26/2008 (3066 reads)
Operational Services Report: November, 2008

Operational Services Report

November 2008

Maintenance

October 20 – November 17, 2008

Building

Work

Complete/In Progress

BEC

- Install Floor Mop Sinks (all cleaning closets)

- Construct new Trades Lab (waiting for overhead door to be installed)

50% Complete

95% Complete

Bras d′Or

- Relocate old Playground (Spring)

In Progress

Cabot

- Installing new Windows in half the Building – Contracted to Stott Aluminum to install (Spring)

In Progress

Cornwallis

- Install Video Security

25% Complete

Cusack

- Install Video Security

50% Complete

Donkin

- Install Video Cameras

Complete

E′Toile De L′Acadie

- Build New Exterior Storage Area

In Progress

F. J. Angot

- Install new Manhole

Complete

General

- Preventive Maintenance on Ventilation Systems

- Regular Boiler Cleaning

- Replacing Broken Windows

- Checking Water Quality

- Install Door Bell for Security (various schools)

- Change EMS Control in Panel - Wiring Project re Security (8 buildings remaining)

- Fire and Life Safety Inspections (2008-09)

- Getting ready for Halloween (Lights/Security)

- Remembrance Day (New flags)

- Update Fall Arrest Training for Custodians, Janitors, Caretakers and Maintenance Personnel

- Sprinkler Quarterly Inspections

Ongoing

Ongoing

Ongoing

Ongoing

95% Complete

95% Complete

In Progress

Complete

Complete

Complete

In Progress

George D Lewis

- 37 Large Plate Glass Windows Broken (Ordered – two week delivery)

In Progress

Gowrie

- Flood – Install new Weeping Tile

Complete

Greenfield

- Pave Back Play Area and Grade Parking Lot

Complete

MacLennan Jr. High

- Security System Upgrade (door contacts)

- Repairs - Fire in Industrial Arts – Door Entrance

Complete

In Progress

Malcolm Munroe

- Fence Players Benches

- Fire in School - waiting for new computers and washing machine

- Upgrade Electrical in Shop (waiting to have wall painted)

Complete

Complete

Complete

Marion Bridge

- Upgrade Front Cement Step with Cement and New Railing

Complete

Memorial High

- Working on Electrical for Vocational Equipment

- Construction of Learning Centre(waiting for ventilation unit and appliances)

In Progress

96% Complete

Mountainview

- 81 Single Pane Windows Broken

Complete

Mount Carmel

- Installing Mop Sinks

80% Complete

Operations

- Repair Floor Joints in Warehouse

Complete

Riverview High

- New P. A. System

- Tender out for two sections of Roof and install

- New Wall in Tunnel (waiting to have painted)

- Install Sound Panels in Music Room

98% Complete

85% Complete

Complete

Complete

Robin Foote

- Installing Roof Fans

- Security System Upgrade (door contacts)

50% Complete

85% Complete

St. Anne

- Repair where Washroom leaks occurred (repairs need to be painted)

Complete

St. Michael′s Jr. High

- Remove Asbestos and Repair Plumbing where Washroom Leak occurred (Repairs to be painted)

Complete

Sydney Academy

-Upgrade Gym and Heating in Classroom

- Install Sound Panels in Music Room

95% Complete

Complete

Sydney Mines Jr. High

- Installing New Windows

65% Complete

Thompson

- Install Ramps from Parking Lot (Postponed to Summer 2009)

- Install Windows in two Sections of Building

80% Complete

Tompkins

- New Power Feed into Building by NS Power

Complete

Technology

November, 2008

S.A.P. daily tasks

Since October we closed 756 routine work orders. Requests such as telecommunications closets cleaning and upgrade in Shipyard, St. Mike′s Jr. High. We also installed a new file server in Sydney Adult and replaced the file server in St. Mike′s Jr. High.

Internet Connectivity

Eastlink internet installs are ongoing. We have only two schools left to change over to the Eastlink fiber optics circuit.

Computers for Schools

Since June, the Technology Department and Computers for Schools installed over 36 computers, 11 network laser printers and one scanner in our School Board. We delivered 18 computers and two printers within the community for charitable donations.

I.E.I.

We have almost completed the second rollout of software installs on the 100 I.E.I. computers in the grade 11 classrooms.

P-12 Refresh

During the month of October we installed, configured and delivered 38 computer systems and eight multimedia projectors.

Transportation

November, 2008

Runs continue to be reviewed for efficiency.

On October 24, 2008, all bus drivers and bus aids received an update on First Aid and CPR.

We have been working on an anti-idling plan and have started a promotion program that will see two schools as a pilot.

On November 18, we visited the schools North of Smokey to review and make some changes in bus routes.

Mechanics had a day of in-servicing October 28 covering computerized diagnostics on engines and transmissions.

We joined with a group from Strait Regional School Board at Riverview High Computer Room.