Maintenance Report
Work Completed or In Progress
November 17, 2008 – January 19, 2009
Building | Work | Complete/In Progress |
BEC | - Install Floor Mop Sinks (all cleaning closets) - Construct new Trades Lab (waiting for overhead door to be installed) - Upgrade Plumbing in Shower Area | 55% Complete Complete In Progress |
Cabot | - Installing new Windows in half the Building – Contracted to Stott Aluminum to install (spring) | In Progress |
Cape Smokey | - Upgrade Secretaries’ Area | Complete |
Cornwallis | - Install Video Security | 25% Complete |
Coxheath | - Re-finish Gym Floor | Complete |
Cusack | - Install Video Security - Install Window in Special Ed Room | 50% Complete Complete |
E’Toile De L’Acadie | - Build New Exterior Storage Area | Complete |
East Bay | - Replace Fire Alarm | Complete |
General | - Preventive Maintenance on Ventilation Systems - Regular Boiler Cleaning - Replacing Broken Windows - Checking Water Quality - Install Door Bell for Security (various schools) - Change EMS Control in Panel - Fire and Life Safety Inspections (2008-09) - Sprinkler Quarterly Inspections | Ongoing Ongoing Ongoing Ongoing 95% Complete 95% Complete In Progress |
Glace Bay Elementary | - Re-lamp Gym and Library | Complete |
Glace Bay High | - Re-lamp Florescent Fixtures throughout building | In Progress |
George D Lewis | - 37 Large Plate Glass Windows Broken (Ordered – two week delivery) | Complete |
MacLennan Jr. High | - Repairs - Fire in Industrial Arts – Door Entrance - Asbestos Abatement in Cleaning Closet - New Ceilings in Cleaning Closet and Storage | 80% Complete Complete 80% Complete |
Memorial High | - Working on Electrical for Vocational Equipment - Construction of Learning Centre | 80% Complete Complete |
Middle River | - Change Security System | Complete |
Mount Carmel | - Installing Mop Sinks - Re-finish Gym Floor | 80% Complete Complete |
North Highland | - Upgrade Secretaries’ Area | Complete |
Riverview High | - New P. A. System - Tender out for two sections of Roof and install - Repairs re fire in Washroom by Office Area - New Learning Centre and Lab - Asbestos Abatement in area for new Learning Centre and Lab - Install Cable Manager for Internet Wires | Complete Complete 90% Complete In Progress Complete Complete |
Robin Foote | - Installing Roof Fans - Security System Upgrade (door contacts) | 50% Complete 85% Complete |
St. Anne | - Replace Gyproc Wall (where window leaking) | Complete |
Sydney Academy | -Upgrade Gym and Heating in Classroom | Complete |
Sydney Mines Jr. High | - Installing New Windows | 94% Complete |
Thompson | - Install Ramps from Parking Lot (postponed to summer 2009) - Install Windows in two Sections of Building | Complete |
Technology Report
January 14, 2009
SAP Daily Tasks
We closed 1027 routine work orders since November 15. Major requests such as telecommunications cabinet at Riverview, major virus clean up at Glace Bay High,  computer lab upgrade at Whitney Pier Memorial and Morrison, upgrade of 64 computers in grade four to six at Glace Bay Elementary, as well as monitor upgrades in two labs at Glace Bay High.
Internet Connectivity
Eastlink internet installs are complete.
Computers for Schools
Since November, the Technology Department and Computers for Schools installed over 207 computers, eight network laser printers, 68 monitors and one scanner in our School Board. We delivered 74 computers within the community as charitable donations.
P-12 Refresh
During November and December we installed, configured and delivered one video camera, one digital still camera, three laptops, four Imac computers and 66 computer systems.